Summary of the content on the page No. 1
SC-7E and SC-10E
ELECTRIC CONVECTION STEAMER
INSTALLATION – OPERATION – MAINTENANCE
BLODGETT OVEN COMPANY
www.blodgett.com
44 Lakeside Avenue, Burlington, Vermont 05401 USA Telephone (800) 331-5842, (802) 860-3700 Fax: (802) 864-0183
1
S00058 Rev A (5/04)
Summary of the content on the page No. 2
IMPORTANT NOTES FOR INSTALLATION AND OPERATION This is the safety alert symbol. It is used to alert you to potential personal injury hazards. Obey all safety messages that follow this symbol to avoid possible injury or death. WARNING: Improper installation, operation, adjustment, alteration, service or maintenance can cause property damage, injury or death. Read the installation, operating and maintenance instructions thoroughly before installing, operating or servicing this equipment. Adeq
Summary of the content on the page No. 3
TABLE OF CONTENTS DESCRIPTION PAGE 1.0 Service Connections ...............................................................................................4 2.0 Installation Instructions..............................................................................................5 3.0 Operation ................................................................................................................9 4.0 Cleaning .................................
Summary of the content on the page No. 4
1.0 SERVICE CONNECTIONS 4
Summary of the content on the page No. 5
2.0 INSTALLATION INSTRUCTIONS This steamer was inspected before leaving the factory. The transportation company assumes full responsibility for safe delivery upon acceptance of the shipment. Immediately after unpacking the steamer, check for possible damage. If the steamer is found to be damaged after unpacking, save the packaging material and contact the carrier within 15 days of delivery. Prior to installation, verify that the electrical service agrees with the specifications on the machine da
Summary of the content on the page No. 6
ELECTRICAL CONNECTION WARNING: Electrical grounding connections must comply with applicable portions of the National Electrical code and/or other local electric codes. WARNING: Disconnect the power supply to the appliance before cleaning or servicing. Make electrical connection through the 1-1/8" (29 mm) diameter hole provided using 3/4" (19mm) trade size conduit. Refer to the wiring diagram located inside the right side panel. Use 90°C minimum insulated wire. PLUMBING CONNECTIONS WARNING: Pl
Summary of the content on the page No. 7
DRAIN CONNECTIONS The drain connection must be 1" (25 mm) IPS down, preferably with one or two elbows only, maximum length 6 feet (1830 mm) and piped to an open gap type drain (Figure 1). Drain pipe should be either iron or copper. DO NOT use PVC pipe – PVC pipe may lose its rigidity or glue may fail. CAUTION: To avoid injury or damage to the steamer, do not connect solidly to any drain connection. WATER QUALITY The water supply connected to the steam generator should meet the following guidelin
Summary of the content on the page No. 8
VENT HOOD Some local codes may require the steamer to be located under an exhaust hood. Information on the construction and installation of ventilating hoods may be obtained from NFPA Standard No. 96, Vapor Removal from Cooking Equipment, (latest edition). START-UP TEST WARNING: The steamer and its parts are hot. Use care when operating, cleaning or servicing the steamer. The cooking compartment contains live steam. Stay clear while opening the door. Once the steamer is installed and all mechan
Summary of the content on the page No. 9
3.0 OPERATION WARNING: Live steam and accumulated hot water in the compartment may be released when the door is opened. WARNING: An obstructed drain can cause personal injury or property damage. CONTROLS Main Power Switch ON - The boiler will automatically fill and begin heating to the preset temperature. OFF - The boiler will drain. DELIME - Closes the drain valve while CLR liquid is being poured into the generator during the delime procedure. Ready Light - Indicates the temperature has reach
Summary of the content on the page No. 10
3.0 OPERATION (Continued) BEFORE FIRST USE Clean the protective oils from all surfaces of the steamer. Use a non-corrosive, grease dissolving commercial cleaner, following manufacturer’s directions. Rinse thoroughly and wipe dry with a soft clean cloth. PREHEAT Turn the main power switch ON. When the READY light comes on, set the timer to 1 minute to preheat the compartment. This should be done when the steamer is first used for the day or whenever the chamber is cold. The door should be closed
Summary of the content on the page No. 11
CONSTANT STEAM FEATURE, (OPTIONAL) A switch has been added to control this feature. It is located below the timer under the heading “COOKING MODE”. TIMED COOKING The switch must be positioned to the right, towards the heading “TIMED COOKING”. The steamer will then operate as described in the previous section. At the end of the cook time an audible buzzer will sound. CONSTANT STEAM COOKING The switch must be positioned to the left towards the heading “CONTINUOUS COOKING”. This mode will give cont
Summary of the content on the page No. 12
COOKING HINTS Your steamer efficiently cooks vegetables or other foods for immediate serving. Steam cooking should be carefully time controlled. Keep hot food holding-time to a minimum to produce the most appetizing results. Prepare small batches, cook only enough to start serving, then cook additional amounts to meet demand. Preparation Prepare vegetables, fruits, meats, seafood, and poultry normally by cleaning, separating, cutting, removing stems, etc. Cook root vegetables in a perforated pan
Summary of the content on the page No. 13
4.0 CLEANING WARNING: DO NOT use cleaning agents that are corrosive. WARNING: Disconnect the power supply to the appliance before cleaning or servicing. At the end of each day, or between cooking cycles if necessary... Turn main power switch OFF. Remove pans and racks from compartment and wash in sink. Wash compartment interior with clean water. Never use steel wool or abrasive scouring pads as they will scratch and ruin the general surface appearance of the steamer. Use warm soapy water with
Summary of the content on the page No. 14
GUIDELINES FOR MAINTAINING STAINLESS STEEL SURFACES There are three things that can break down stainless steel and allow corrosion to develop: 1) Abrasion; 2) Deposits and water; 3) Chlorides. Avoid rubbing with steel pads, wire brushes, or scrapers that can leave iron deposits on stainless steel; instead, use plastic scouring pads or soft cloths. For stubborn stains, use products such as Cameo, Talc, or Zud First Impression. Always rub parallel to polish lines or with the grain. Hard water can
Summary of the content on the page No. 15
5.0 MAINTENANCE REMOVAL OF SCALE DEPOSITS WARNING: Read and follow instructions on the CLR bottle. Use plastic or rubber gloves to avoid skin contact. IF CLR comes in contact with skin, rinse and clear water. 1. Drain steam generator tank by setting ON/OFF switch to off. Set cooking timer to “OFF”. 2. Set switch to de-lime. This closes drain valve. 3. Unscrew plug in deliming port at rear of unit. Insert hose in delime fitting. Pour 28 ounces of solution into generator slowly to avoid spillage.
Summary of the content on the page No. 16
6.0 TROUBLESHOOTING PROBLEM POSSIBLE CAUSES Cold water flows continuously into drain Either or both solenoid valves are not when steamer is OFF. closing. Contact your authorized service agency to repair or replace solenoid valves. Water overflowing into cooking Problem with operating probe caused by compartment. either: 1. Short between probe terminal and body of steamer. Contact your authorized service agency. 2. Excessive scale build-up on probe. Contact your authorized service agency. Have wa
Summary of the content on the page No. 17
7.0 SERVICE ADJUSTMENT FOR HIGH ALTITUDE LOCATIONS NOTICE: Contact the factory, the factory representative or local service company to perform maintenance and repairs. The steamer has been factory set so that when it is ON and during the READY phase, it will maintain water temperature in the steam generator tank at approximately 205 degrees Fahrenheit (just below water boiling point). However, for high altitude locations, an authorized servicer must adjust the steamer to achieve this temperature
Summary of the content on the page No. 18
8.0 SERVICE (Continued) WATER OVERFLOWS INTO COOKING COMPARTMENT When steamer is first turned on for the day, and the following conditions occur: - READY light does not come on after about 15 minutes, - Water begins to overflow into cooking compartment, - Water fill solenoid valve is open, then any or all of these symptoms may indicate a problem with the operating probe due to either: 1. A short between the operating probe terminal and body of the steamer. Call your authorized servicer. 2. Exces