ページ1に含まれる内容の要旨
INSTALLATION GUIDE FOR
EVOLUTION™ AIR BATHS
MODEL 2422V.068C 5' x 32"
MODEL 2771V.068C 5' x 36"
MODEL 2645V.068C OVAL
MODEL 7236V.068C 6' x 36"
MODEL 2425V.168C 5' x 32" IA-RHO
MODEL 2425V.268C 5' x 32" IA-LHO
THANK YOU...
for selecting an American Standard bath. Your new bath is shipped to you after careful inspection. The air bath is
completely assembled with air blower and system piping. All you need to finish the installation are your selected
fittings and electrical connect
ページ2に含まれる内容の要旨
TABLE OF CONTENTS: Safety Instructions............................................................................Page General Information..........................................................................Page 4 Optional Components.......................................................................Page 4 Specifications....................................................................................Page 5 Roughing-in Reference........................................................
ページ3に含まれる内容の要旨
IMPORTANT SAFETY INSTRUCTIONS INSTRUCTIONS PERTAINING TO A RISK OF FIRE, ELECTRIC SHOCK OR INJURY TO PERSONS READ AND FOLLOW ALL INSTRUCTIONS! ! WARNING: Risk of personal injury. Do not permit children to use this unit without adult supervision. ! WARNING: Risk of personal injury. Do not operate this unit without the guard over the suction fitting. WARNING: Risk of electric shock. Do not permit electrical appliances (hair dryer, telephone, radio, etc.) within ! 0 inches (1524mm) of this unit
ページ4に含まれる内容の要旨
General Installation Information Carefully uncrate and inspect your new bath for any shipping damage. If such damage is found, report it to your vendor immediately. After inspection and during installation, protect the bath from construction damage. Before installation, and before enclosing with wallboard, tile, etc., the bath must be filled with water and operated to check for leaks that may have resulted from shipping damage or mishandling! Do not make unauthorized modifications to the air
ページ5に含まれる内容の要旨
SPECIFICATIONS: L W J H C A SIDE VIEW END VIEW DRAIN / OVERFLOW B GENERAL SPECIFICATIONS FOR EVOLUTION AIR BATHS Description Dimensions Drain / Height to Cut Out Rough-In Tub Edge to Weight with Product Apron / Gallon to L-W-H Overflow Underside Pier Recess Centerline Water / Floor Weight Mounting Overflow of Deck: C G x F E x D Overflow: J Loading 2422V.0C L 1524mm (0") A 20-1/" C 20" 5-1/2" 0-/1" mm 0lb (1kg)/ 74 lb. Optional 74 gal. 5' x 2" W 1mm (2") (511 mm) (50 mm) (145
ページ6に含まれる内容の要旨
ROUGHING-IN REFERENCES 6' x 36" (MODEL 7236V.068C) 5' x 32" (MODEL 2422V.068C) 72" 0" (12mm) 11" (1524mm) (27mm) -1/4" (mm) 1-/4" 1-/4" (4mm) " 7-/4" (4mm) (7mm) " (17mm) " (7mm) 2" " (14mm) (1mm) (152mm) " (152mm) CUT OUT IN FLOOR 7-/4" FOR DRAIN CUT OUT IN FLOOR (17mm) FOR DRAIN -1/4" 11" (mm) (27mm) 5' x 36" (MODEL 2771V.068C) OVAL (MODEL 2645V.068C) 0" " (1524mm) (17mm) 11-1/4" 11" (2mm) (27mm) 1-/4" -1/4" (44mm) (mm) 1" (457mm) " CUT OUT
ページ7に含まれる内容の要旨
INSTALLATION AND FRAMING INSTRUCTIONS The variety of installations possible for this air bath may require framing procedures other than those shown. Locate studs as needed. Ensure roughing-in dimensions are proper, plumb and square. Provisions must be made in all installations for an access opening for servicing the air blower and controls. It is strongly recommended that an additional opening be provided for access to the drain components. The apron should not be used as the primary access o
ページ8に含まれる内容の要旨
TYPICAL FLANGE MOUNTING DETAIL SUGGESTED AIR BATH / BATH INSTALLATION METHOD WOOD STUDS STEEL STUDS STEEL STUD STUD WASHER WATERPROOF DRYWALL WATERPROOF DRYWALL OR CEMENT BOARD OR CEMENT BOARD TILE TILE ROOFING NAIL SEALANT SEALANT 4" (102mm) DRYWALL SCREW TUB TUB 1 x (25 x 7mm) WOOD 1 x (25 x 7mm) WOOD STRINGER FULL LENGTH STRINGER FULL LENGTH SECURE THE BATH TO THE STUDS AS SHOWN FOR WOOD OR STEEL STUD CONSTRUCTION. UNDER DECK MOUNTING INSTRUCTIONS Please note that care must be
ページ9に含まれる内容の要旨
AIR BATH ELECTRICAL INSTALLATION INSTRUCTIONS All wiring must be performed by a licensed electrician in accordance with the national electrical code and all other applicable codes. WARNING: When using electrical products, basic precautions should always be observed, including the following: ! 1. DANGER: RISK OF ELECTRIC SHOCK! Connect only to a circuit protected by a ground-fault circuit interrupter. 2. Permit access for servicing blower as noted. . All building materials and wiring should
ページ10に含まれる内容の要旨
DRAIN CONNECTION AND SYSTEM TEST Using recommended drain assembly, connect the bath drain to waste line in accordance with the drain assembly instructions. Tighten all drain joints securely. Clean the air bath and fill with water to a point 2" above the top of the highest jet. Check for leaks around all piping connections while the air bath is running. POST INSTALLATION CLEAN-UP Remove all construction debris from bath. Tile grout can be removed with a wooden popsicle stick or tongue depressor
ページ11に含まれる内容の要旨
REMOTE BLOWER LOCATION OPTION IMPORTANT! It is not necessary that the blower motor be relocated. This option is provided for the case that a particular installation makes this effort practical. NOTE: Relocating blower motor from factory installed location, see photo W, will require disassembly of air blower from mounting board. Keep all hardware for reattachment at new location. Additional hardware will be required depending upon final desired position of air blower. Follow all instructions
ページ12に含まれる内容の要旨
AS America, Inc. Limited Lifetime Warranty For Evolution™ Acrylic Air Baths AS America, Inc. (”American Standard”) warrants to the original consumer purchaser that it will, at its option, repair or replace this air bath or any of its parts that are found by American Standard, in its sole judgment, to be defective under normal residential use and maintenance so long as it is owned by the original consumer purchaser. This warranty shall only become effective upon receipt by American Standard of