ページ1に含まれる内容の要旨
OWNER`S MANUAL
DROLET EPA WOODSTOVES
HT-1200 HT-1600 HT-2000
US ENVIRONMENTAL PROTECTION
AGENCY PHASE II CERTIFIED
WOODSTOVES
Vérified and tested following
ULC S627 et UL 1482 Standards by:
Intertek Testing Services
READ AND KEEP THIS MANUAL FOR REFERENCE
Manufactured by : STOVE BUILDER INTERNATIONAL INC.
1700, Léon-Harmel, Québec (Québec) G1N 4R9
Tel : ( 418 ) 527-3060
Fax : ( 418 ) 527-4311
www.drolet.ca
990810/45060A_Feb 03
ページ2に含まれる内容の要旨
TABLE OF CONTENTS INTRODUCTION................................................................................................................. 2 TECHNICAL SPECIFICATIONS ......................................................................................... 3 ASSEMBLY......................................................................................................................... 4 PEDESTAL AND DECORATIVE SIDEWALL INSTALLATION........................................ 4 BRICKS INS
ページ3に含まれる内容の要旨
INTRODUCTION SBI INC., one of the most important wood stove and fireplace manufacturers in Canada, congratulates you on your purchase and wishes to help you get maximum satisfaction from your wood stove. In the pages that follow, we will give you advice on wood heating and controlled combustion as well as technical specifications regarding installation, operation and maintenance of the model you have chosen. The instructions pertaining to the installation of your wood stove comply wit
ページ4に含まれる内容の要旨
TECHNICAL SPECIFICATIONS HT-1200 HT-1600 HT-2000 Combustion Type: Wood Wood Wood 2 2 2 Recommended Surface 600 à 1 200 ft 900 à 1 600 ft 1 000 à 2 000 ft 2 2 2 (56 à 112 m ) (84 à 149 m ) (93 à 186 m ) 36 000 BTU/h 40 000 BTU/h 60 200 BTU/h Heating Capacity : E.P.A : (10,5kW) (11,7 kW) (17,6 kW) 45 000 BTU/h 70 000 BTU/h 95 000 BTU/h Real : (13,2 kW) (20,5 kW) (27,8 kW) Efficiency : 73% 71,3% 72,2% Average Emission: 6,5 g/h 3,3 g/h 3,8 g/h Colours : Standard Models : Metallic Bl
ページ5に含まれる内容の要旨
ASSEMBLY PEDESTAL AND DECORATIVE SIDEWALL INSTALLATION Pedestal Installation : 1. Remove all bricks and insulations in the appliance. 2. Slowly, lay down the stove on his back. 3. Install legs or the pedestal with the supplied nuts and bolts. Stand up the stove and place it with the required clearances. Note that there is eight holes in the bottom of the stove but only four will align with the pedestal. 4. Slide the front part of the pedestal base around the pedestal and f
ページ6に含まれる内容の要旨
BRICKS INSTALLATION (HT-1200) • Refractory bricks are to be installed according to figure 4. • In both stoves, the baffle brick must be pushed as close to the front as possible onto its metallic support. • The upper bricks (2) must lay on the vertical bricks (4) grove • Note that a plain brick is supplied instead of a ashtray cap on standard models. Figure 3: HT-1200 & HT-1200 DELUXE Bricks 5
ページ7に含まれる内容の要旨
BRICKS AND INSULATION INSTALLATION (HT-1600) 1. Remove from the stove all bricks and insulation. 2. Install all side bricks (12 x 4 1/2" x 9") 3. Install the back bricks (6 x 4 1/2" x 9") 4. Install the bottom bricks (4 x 4 1/2" x 9") + (2 x 6 " x 8") + (1 x 6" x 2") for HT-1600 and (4 x 4 1/2" x 9") + (2 x 6" x 7") for HT-1600 Deluxe. 5. Install the "T" shape support and the bricks (4 x 4 1/2" x 9") + (2 x 3" x 9"). 6. Install the baffle bricks (4 x 4 1/2" x 9") + (2 x 3" x
ページ8に含まれる内容の要旨
BRICK AND INSULATION INSTALLATION (HT-2000) The stove is normally supplied with secondary air tubes in position. To install the baffle bricks and white ceramic insulation, it’s necessary to remove the two front secondary air tubes. First place only one baffle brick and one white ceramic insulation. Use the same method to put the other baffle brick and insulation. Put back in place the secondary air tubes. Install the yellow insulation and the 6" x 8" or 6" x 6" bricks. Install the
ページ9に含まれる内容の要旨
AIR TUBES INSTALLATION (HT-2000): The secondary air tubes are painted different colours . The back tube is yellow, the middle on is red and the front is unpainted. Before installing, make sure the locating holes in the tubes (holes near one end of the tube) are on the left side. Insert one tube in the right side air channel and slide it to the right as much as possible. Bring the left end of the tube aligned with the ring welded to the left air channel. Move the tube to the left until the
ページ10に含まれる内容の要旨
DOOR ADJUSTMENT In order for your stove to operate properly, the door should be adjusted periodically to provide an air tight fit. To adjust: • Remove the lock pin (spring pin) by pulling and turning it using pliers ("wise grip") • Turn the handle counter clock wise one turn to increase pressure • Re-install the lock pin (spring pin) with a small hammer Figure 7: Door Adjustment 9
ページ11に含まれる内容の要旨
THE BENEFITS OF INSTALLING A BLOWER A blower can be installed at the back of your DROLET stove. This option is necessary if you wish to redistribute into a room the heat trapped at the back of your stove. By forcing hot air toward the front, the blower enables you to extend the radiation power of your stove. You can purchase this option through your DROLET dealer. Make sure to specify this part number: #AC02050. You can also install a thermodisc to enable the blower to start or stop au
ページ12に含まれる内容の要旨
INSTALLATION SAFETY NOTICE • IF THIS STOVE IS NOT PROPERLY INSTALLED, A HOUSE FIRE MAY RESULT. TO REDUCE THE RISK OF FIRE, FOLLOW THE INSTALLATION INSTRUCTIONS. FAILURE TO FOLLOW INSTRUCTIONS MAY RESULT IN PROPERTY DAMAGE, BODILY INJURY, OR EVEN DEATH. • CONSULT YOUR MUNICIPAL BUILDING DEPARTMENT OR FIRE OFFICIALS ABOUT RESTRICTIONS AND INSTALLATIONS REQUIREMENTS IN YOUR AREA. • USE SMOKE DETECTORS IN THE ROOM WHERE YOUR STOVE IS INSTALLED. • KEEP FURNITURE AND DRAPES WELL AWAY FROM
ページ13に含まれる内容の要旨
FLOOR PROTECTOR Your wood stove should be placed on a non-combustible surface. The floor protector should be under the stove, eighteen inches beyond the front and eight inches beyond each side of the fuel loading and ash removal opening. If there is a horizontal section of chimney connector, the floor protector should go under it and two inches beyond each side. The floor protector should exceed the stove as follows: FRONT SIDES BACK 18’’ 8’’ 8’’ (460 mm) (200 mm) (200 mm)
ページ14に含まれる内容の要旨
CLEARANCES It is of utmost importance that the clearances to combustible material be scrupulously respected upon installation of the stove you have selected. Refer to the tables below : Figure 8: Clearances to combustibles CANADA Single pipe / Double pipe Model A B C D E F HT-1200 15/10 16/16 10/8 20.3/15.3 27.3/27.3 21.8/19.8 HT-1200 Deluxe 15/10 8/8 7/6 20.4/15.4 20/20 19.4/18.4 HT-1600 15/12 16/16 12/10 20.8/17.8 28.7/28.7 25.2/23.2 HT-1600 Deluxe 15/12 14/12 12/8 20.8/17.8 27.2
ページ15に含まれる内容の要旨
REDUCED CLEARANCES You may decrease the clearances by installing heat radiation shields between the walls or the ceiling and the stove. These heat radiation shields must be installed permanently, and can include sheet metal, a rigid non-combustible sheet or a masonry wall. Clearances of not less than 1" (25 mm) and not more than 3" (76 mm) between the bottom of the shield and the floor and not less than 3" (76 mm) between the top of the shield and the ceiling must be respected to allow
ページ16に含まれる内容の要旨
CHIMNEY Your wood stove may be hooked up with a factory built or masonry chimney. If you are using a factory built chimney, it must comply with UL 103 or ULC S629 standards; therefore it must be a Type HT (2100°F). It is extremely important that it be installed according to the manufacturer's specifications. If you are using a masonry chimney, it is important that it be built in compliance with the specifications of the National Building Code. It must be lined with fire clay bricks, m
ページ17に含まれる内容の要旨
CHIMNEY CONNECTOR (STOVE PIPE) Your chimney connector and chimney must have the same diameter as the stove outlet. If this is not the case, we recommend you contact your dealer in order to insure there will be no problem with the draught. The stove pipe must be made of aluminized or cold roll steel with a minimum thickness of 0.021" or 0.53 mm. It is strictly forbidden to use galvanized steel. Your smoke pipe should be assembled in such a way that the male section of the pipe faces down
ページ18に含まれる内容の要旨
TYPICAL INSTALLATIONS FACTORY BUILT CHIMNEY: RAIN CAP ROOF FLASHING 18" CLEARANCE RADIATION SHIELD WALL RADIATION SHIELD WALL SUPPORT CEILING SUPPORT Wall installation Vertical installation 17
ページ19に含まれる内容の要旨
MASONRY CHIMNEY: Clay liner Thimble Clean out door 18
ページ20に含まれる内容の要旨
FACTORY BUILT THIMBLE: 19