SET-UP INSTRUCTIONS & PRE-OPERATION CHECKLIST
SNAPPER LARGE FRAME ZERO TURNING Z-RIDER with MID MOUNT MOWER
INTRODUCTION: These instructions cover the set-up of the Snapper Large Frame Mid Mount Z-Rider Mower.
Complete each of the following steps carefully. Review and complete each item as instructed on the Pre-Operation
checklist. The Snapper Product Registration card must be filled out and sent to Customer Service department at
Snapper when completed.
IMPORTANT: The battery for this unit is ma
Inhaltszusammenfassung zur Seite Nr. 2
B. Attach roll bar to side bars, securing with two 1/2- BLACK (NEGATIVE) CABLE RED (POSITIVE) CABLE 13 x 3-3/4” hex bolts and lock nuts through the rear hinge holes. See Figure 4. NOTE: Slip stop brackets over hinges before installing hardware. See Figure 4. C. Raise roll bar to fully upright position, aligning locking holes in roll bar with corresponding holes in side bars. Insert locking pin through each forward hole, and secure with connected bridge pin. Install plastic knobs into threade
Inhaltszusammenfassung zur Seite Nr. 3
STEP 10: MOWER DECK ADJUSTMENT (LEVELNESS) IMPORTANT: Re-check fluid level after operating machine SIDE to SIDE and FRONT to REAR for several minutes and adjust level as needed. If one or Before making deck leveling adjustments, inflate rear tires to both of the wheel drive systems is not pulling properly, the 12 PSI and front tires to 25 PSI. When adjusted correctly, hydraulic system may need to be purged of entrapped air. the deck will be level side to side within 1/8”, have a low cut Refer t
Inhaltszusammenfassung zur Seite Nr. 4
STEP 13: HYDRAULIC SYSTEM, PURGING HYDRAULIC When initially putting hydraulic system into service, one or RESERVOIR both of the wheel drives may not pull properly. This is likely to be caused by air entrapped in the system. If you experience a pulling issue during initial setup or after com- pleting repairs, perform the following procedure to purge the air from one or both of the hydraulic drive systems. IMPORTANT: WHEN REPLACING THE HYDRAULIC FLUID FILTER, PRE-FILL WITH OIL (SAE 20W50 API SL) B
Inhaltszusammenfassung zur Seite Nr. 5
NOTES 5
Inhaltszusammenfassung zur Seite Nr. 6
PRE-OPERATION CHECKLIST Snapper has completed initial adjustments and performed operational tests prior to shipping the machine. Due to the possible effects of shipping, handling and storage, Snapper intends for all of the following items to be verified and necessary final adjustments made at time of setup. It remains good practice and is strongly recommended that all the items also be checked prior to placing the machine into service. It is very important that setup is veri- fied and all operat