ملخص المحتوى في الصفحة رقم 1
C120-H007-06EN
Front Cover
SPARC M10 Systems/
SPARC Enterprise/
PRIMEQUEST
COMMON INSTALLATION PLANNING
MANUAL
ملخص المحتوى في الصفحة رقم 2
ملخص المحتوى في الصفحة رقم 3
FOR SAFE OPERATION Handling of This Manual This manual contains important information regarding the use and handling of this product. Read this manual thoroughly. Use the product according to the instructions and information available in this manual. Keep this manual in hand for further understanding. Fujitsu makes every effort to prevent users and bystanders from being injured or from suffering from damages to their property. Use the product according to this manual. ABOUT THIS PRODUCT
ملخص المحتوى في الصفحة رقم 4
TRADEMARKS ACKNOWLEDGEMENTS UNIX is a registered trademark of The Open Group in the United States and other countries. The contents of this manual shall not be disclosed in any way or reproduced in any media without the express written permission of Fujitsu Limited. All Rights Reserved, Copyright © FUJITSU LIMITED 2002-2011 C120-H007-05EN
ملخص المحتوى في الصفحة رقم 5
Revision History (1/1) Revised section Edition Date Details (Added/Deleted/Altered) 01 2002-10-31⎯⎯ 02 2005-09-15 Entire manual (Altered) • Technical brush-up • Modification of the manual title • Addition of PRIMEQUEST Section 3.3.2 • Modification of the concept of units (Altered/Added) operational grouping • Addition of description for concentration of small equipment Section 5.2.2 (Added) • Addition of conditions for using mobile phones 03 2008-04-16 Entire manual (Altered) • Modificat
ملخص المحتوى في الصفحة رقم 6
ملخص المحتوى في الصفحة رقم 7
Preface 1 This manual describes the requirements and concepts of installation and facility planning that pertain to the setup of SPARC Enterprise and PRIMEQUEST. Installation and facility planning requires full review with Fujitsu representatives in charge according to the instructions presented herein. This manual is intended for site planners preparing for the server system installation. Use this manual to review server system installation plans or to run and administer the server syst
ملخص المحتوى في الصفحة رقم 8
Preface CHAPTER 6 Power Supply Facilities This chapter describes the power supply requirements, power supply facilities, grounding plans, power distribution boards, and power distribution routes for the server systems. CHAPTER 7 Protection Against Lightning This chapter describes the safeguards necessary to protect server systems against destructive lightning surge voltages. CHAPTER 8 Security Actions This chapter describes the actions necessary to ensure server system security. Appendix
ملخص المحتوى في الصفحة رقم 9
Preface Other Reference Manuals When installing the SPARC Enterprise or PRIMEQUEST, read the installation guide for each model first. For the readers • If you find any inconvenience with the description or incorrect explanation in this manual, please fill in the "Comment Form" sheet at the back of this manual and forward it to the address described on the sheet. • This manual is subject to be revised without prior notice. C120-H007-05EN iii
ملخص المحتوى في الصفحة رقم 10
ملخص المحتوى في الصفحة رقم 11
Contents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i CHAPTER 1 Installation Planning Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1.1 Office Installation and Computer Room Installation . . . . . . . . . . . . . . . . . .
ملخص المحتوى في الصفحة رقم 12
Contents 3.3.1 Hardware constraints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 3.3.2 Operational considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 3.4 Air Conditioners . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 3.4.1 Air conditioning units . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 3.4.2 Air conditioning piping . . . . . . . . . . . . .
ملخص المحتوى في الصفحة رقم 13
Contents 4.5.3 Installing temperature/humidity sensors . . . . . . . . . . . . . . . . . . . . . . . 54 4.5.4 Taking in fresh air . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54 4.5.5 Preventing dew condensation in underfloor ventilation . . . . . . . . . . . 55 4.5.6 Preventing water leaks and installing detectors . . . . . . . . . . . . . . . . . 56 4.5.7 Installing a backup unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
ملخص المحتوى في الصفحة رقم 14
Contents 6.8.1 Test voltage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 6.8.2 Phase and grounding cable insulation test . . . . . . . . . . . . . . . . . . . . . 89 6.8.3 Interphase insulation testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89 CHAPTER 7 Protection Against Lightning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91 7.1 Protection of AC Line . . . . . . . . . . . . . . . . . . . . . . . . .
ملخص المحتوى في الصفحة رقم 15
Contents Figures Figure 2.1 Slit floor panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Figure 2.2 Floor panels with an airflow control damper . . . . . . . . . . . . . . . . . . . . 21 Figure 2.3 Air flow control panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 Figure 3.1 Concept of units operational grouping . . . . . . . . . . . . . . . . . . . . . . . . . 27 Figure 4.1 Direct blowing setup . . .
ملخص المحتوى في الصفحة رقم 16
ملخص المحتوى في الصفحة رقم 17
Contents Tables Table 2.1 Ceiling heights. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Table 2.2 Raised floor heights of free-access floors . . . . . . . . . . . . . . . . . . . . . . . 18 Table 2.3 Strengths and surface materials of free-access floor panels . . . . . . 19 Table 3.1 Kinds, uses, and locations of power supply facilities . . . . . . . . . . . . . 30 Table 4.1 Recommended temperatures and humidities for computer rooms . 40 Table 4
ملخص المحتوى في الصفحة رقم 18
ملخص المحتوى في الصفحة رقم 19
CHAPTER 1 Installation Planning Overview 1 This chapter defines the general requirements for server system installation planning and for the facilities used to house server systems. Successful planning ensures system installation efficiency now and in the future, assuring system reliability, convenience, and functionality. The users wishing to install a server system must make both the site and associated facilities available, and also develop meticulous installation plans to ensure that
ملخص المحتوى في الصفحة رقم 20
CHAPTER 1 Installation Planning Overview A server system involving equipment that is too large to fit into the available office space or a mixture of equipment having a combined heat dissipation over about 21 MJ/h (20000 Btu/h) would need to be installed in facilities meeting the computer room installation requirements. (1) Equipment suitable for office installation Equipment meeting any of the following requirements is suitable for office installation. Equipment that operates from a power