Installation Manual of Room Air Conditioner
Read this manual before installation
Explain sufficiently the operating means to the user
according to this manual.
Necessary Tools for Installation
1.Driver 5.Torque wrench(17mm,22mm,26mm) 9.Nipper 12.Reamer
2.Hacksaw 6.Pipe cutter 10.Gas leakage detector or
3.Hole core drill 7.Flaring tool soap-and-water solution
4.Spanner(17,19 and 26mm) 8.Knife 11.Measuring tape
Drawing for the install
ملخص المحتوى في الصفحة رقم 2
140 500 140 Floor fixing dimensions of the outdoor unit (Unit:mm) Fix the unit to concrete or block with bolts( 10mm) and nuts firmly and horizontally. Fixing of outdoor unit When fitting the unit to wall surface, roof or rooftop, fix a supporter surely with nails or wires in consideration of earthquake and strong wind. If vibration may affect the house, fix the unit by attaching a vibration-proof mat. Indoor Unit Outdoor Unit Selection of Installation Place Place, robust not causing vibration
ملخص المحتوى في الصفحة رقم 3
Indoor unit 1.Fitting of the Mounting Plate and Positioning of the wall Hole When the mounting plate is first fixed 1.Carry out, based on the neighboring pillars or lintels, a proper leveling for the plate to be fixed against the wall, then temporarily fasten the plate with one steel nail. 2. Make sure once more the proper level of the plate, by hanging a thread with a weight from the central top of the plate, then fasten securely the plate with the attachment steel nail. 3. Find the wall
ملخص المحتوى في الصفحة رقم 4
Indoor unit 3.Installation of the Indoor Unit Drawing of pipe Rear piping Draw pipes and the drain hose, then fasten them with the adhesive tape Left Left-rear piping In case of left side piping, cut away, with a nipper, the lid for left piping. In case of left-rear piping, bend the pipes according to the piping direction to the mark of hole for left-rear piping which is marked on heat insulation materials. 1. Insert the drain hose into the dent of heat insulation materials of indoor unit. 2. In
ملخص المحتوى في الصفحة رقم 5
1(L) 2(N) 3(C) Indoor unit When connecting the cable after installing the indoor unit 1. Insert from outside the room cable into left side of the wall hole, in which the pipe has already existed. 2. Pull out the cable on the front side, and connect the cable making a loop. When connecting the cable before installing the indoor unit Insert the cable from the back side of the unit, then pull it out on the front side. Loosen the screws and insert the cable ends fully into terminal block, then t
ملخص المحتوى في الصفحة رقم 6
Outdoor unit 1.Installation of Outdoor Unit Drawing for the installation of indoor and outdoor units Install according to 2.Connection of pipes To bend a pipe, give the roundness as large as possible not to crush the pipe. Connecting the pipe of gas side first makes working easier. The max vertical distance between the indoor unit and the outdoor unit is 5 m. Flare nut Half union Forced fastening without careful centering may damage the threads and cause a leakage of gas. Fastening torque Pipe D
ملخص المحتوى في الصفحة رقم 7
Outdoor unit 5.Purging Method: Push the air out of the indoor unit and piping as followes: (1) Remove the valve cap on 2-way valve in outdoor unit. (2) Loosen by 1/2 turn the flare nut of 3-way valve gas pipe, which is conneted to 2-way valve 9.52mm(3/8") 3-way valve. 6.35mm(1/4") 12.7mm(1/2") (3) Loosen 2-way valve by 90o using hexagon wrench, and after approx. 10 sec tighten it up. Gas comes out through flare nut on wide pipe. If no gas is discharged, tighte
ملخص المحتوى في الصفحة رقم 8
1.Power Source Installation The power source must be exclusively used for air conditioner. (Over I0A) In the case of installing an air conditioner in a moist place, please install an earth leakage breaker. For installation in other places, use a circuit breaker as far as possible. 2.Cutting and Flaring Work of Piping Pipe cutting is carried out with a pipe cutter and burs must be removed. After inserting the flare nut, flaring work is carried out. A Pipe diameter( ) Size A(mm) Liquid side 6.3